My experience
2020 - 2020
job
Lead Planning Engineer - TREE Program
OMV Petrom.
Project name Tank Farm Automatization/Management System, Coke Drums Replacement, C4 Upgrade, C3+ Recovery
Client name
OMV Petrom
Work location Brazi, Romania
Tasks
- Facilitating Schedule Risk Analysis Workshops, quantitative modelling, and associated float recommendations and critical path analysis to the Final Project Schedule
- Review, validate and incorporate contractor, subcontractor and third party engineering, procurement and construction schedules into the PROJECT performance
- measurement baseline,
- Provide Earned Value and reporting and performance measurements against PROJECT baseline schedule i.e. trends, deviations, delayed construction, procurement and/or
- engineering deliverables,
- Support in Quantitative and Qualitative Risk Analysis workshops.
Client name
OMV Petrom
Work location Brazi, Romania
Tasks
- Facilitating Schedule Risk Analysis Workshops, quantitative modelling, and associated float recommendations and critical path analysis to the Final Project Schedule
- Review, validate and incorporate contractor, subcontractor and third party engineering, procurement and construction schedules into the PROJECT performance
- measurement baseline,
- Provide Earned Value and reporting and performance measurements against PROJECT baseline schedule i.e. trends, deviations, delayed construction, procurement and/or
- engineering deliverables,
- Support in Quantitative and Qualitative Risk Analysis workshops.
Procurement, Management, Engineering, Workshops, Support, Risk analysis
2014 - 2019
job
Site Based Project Planner - Offshore Wind Farm Construction
Siemens Gamesa Renewable Energy.
Project name Dan Tysk, Gode Wind 1+ 2, Veja Mate, Rentel, Hornsea 1
Client name
Vattenfall Vindkraft A/S, Orsted, Veja Mate Co., Rentel
Work location Esbjerg, DK
Tasks
- Daily coordination with Site Management onshore and offshore
- Prepare weekly and monthly look ahead plan
- Record additional work including NC and trouble shooting in Primavera
- Record Adverse Weather in Primavera
- Record Adverse Events in primavera in order to give full transparency on progress
- Weekly coordination with Site/Project Commercial Manager and with Project Claims Manager to review the EOT schedule and Hours Downtime claims.
- Periodic coordination with Installation/Technical Leads to define/review the Additional Client Work schedules and Retrofit Work plans.
- Daily coordination with Offshore Site Manager to ensure the accuracy of the Daily Progress Reports Database.
- Monthly Construction KPI Dashboard preparation and review with CM.
- Weekly reporting of man hours spent by discipline and location.
- Weekly reporting of lead times for installation and commissioning, by location.
- Weekly reporting of the status and forecast of the NonStandard Works in terms of man hours spent, earned and forecasts of remaining works.
- Weekly Project Execution Overview preparation.
Client name
Vattenfall Vindkraft A/S, Orsted, Veja Mate Co., Rentel
Work location Esbjerg, DK
Tasks
- Daily coordination with Site Management onshore and offshore
- Prepare weekly and monthly look ahead plan
- Record additional work including NC and trouble shooting in Primavera
- Record Adverse Weather in Primavera
- Record Adverse Events in primavera in order to give full transparency on progress
- Weekly coordination with Site/Project Commercial Manager and with Project Claims Manager to review the EOT schedule and Hours Downtime claims.
- Periodic coordination with Installation/Technical Leads to define/review the Additional Client Work schedules and Retrofit Work plans.
- Daily coordination with Offshore Site Manager to ensure the accuracy of the Daily Progress Reports Database.
- Monthly Construction KPI Dashboard preparation and review with CM.
- Weekly reporting of man hours spent by discipline and location.
- Weekly reporting of lead times for installation and commissioning, by location.
- Weekly reporting of the status and forecast of the NonStandard Works in terms of man hours spent, earned and forecasts of remaining works.
- Weekly Project Execution Overview preparation.
Database, Management, German, Offshore, Primavera, KPI, Site manager, Forecast, Manager
2013 - 2014
job
Lead Planner
Netco Engineering Ltd.
Project name Egina FPSO Detailed Engineering Project
Client name
Total
Work location Lagos, Nigeria
Tasks
- Focal point for planning and scheduling team
- Schedule handling, maintaining and reporting for all locations
- Coordination of updating, maintaining & reporting for integrated schedule.
- Identify potential slippages/ actual slippages and report to PMT.
- Identify and monitor critical activities. Highlight to PMT.
- Identify the reasons of delay and highlight to PMT
- Interface management between all discipline for planning and scheduling activities.
- Review the activities delayed and look ahead for all locations
- Issue Weekly and Monthly Report to SHI
- Attend internal Weekly meeting
- Provide scheduling update during internal Weekly meeting - Key milestones, Progress update, Work achieved & plan.
- Modeling Progress Coordinator
Client name
Total
Work location Lagos, Nigeria
Tasks
- Focal point for planning and scheduling team
- Schedule handling, maintaining and reporting for all locations
- Coordination of updating, maintaining & reporting for integrated schedule.
- Identify potential slippages/ actual slippages and report to PMT.
- Identify and monitor critical activities. Highlight to PMT.
- Identify the reasons of delay and highlight to PMT
- Interface management between all discipline for planning and scheduling activities.
- Review the activities delayed and look ahead for all locations
- Issue Weekly and Monthly Report to SHI
- Attend internal Weekly meeting
- Provide scheduling update during internal Weekly meeting - Key milestones, Progress update, Work achieved & plan.
- Modeling Progress Coordinator
Management, Engineering, Coordinator
2012 - 2013
job
Project Control Scheduler
Linde Engineering GMBH.
Project name Tobolsk Polypropylene Plant
Client name
SIBUR Holding
Work location Tobolsk, Russia
Tasks
- Prepared the re-baseline construction schedule for the remaining works at the Polypropylene Plant.
- Prepared the manpower histograms and s-curves for the re-baseline schedule.
- Integrated the Contractors schedules, resource loaded and follow-up their weekly updates.
- CPM analysis and peer review with the construction team and with the Client in order to ensure the achievement of the MC milestones in time and within budget
- Weekly/Monthly updates of Primavera schedules.
- Weekly meetings chaired with Contractors to align the status of works with the schedule and all critical items are recognized.
- Weekly/Monthly progress reports prepared, revised and submitted to the Client and Project management Team
- Coordinate the Contractors Planning and scheduling staff.
Client name
SIBUR Holding
Work location Tobolsk, Russia
Tasks
- Prepared the re-baseline construction schedule for the remaining works at the Polypropylene Plant.
- Prepared the manpower histograms and s-curves for the re-baseline schedule.
- Integrated the Contractors schedules, resource loaded and follow-up their weekly updates.
- CPM analysis and peer review with the construction team and with the Client in order to ensure the achievement of the MC milestones in time and within budget
- Weekly/Monthly updates of Primavera schedules.
- Weekly meetings chaired with Contractors to align the status of works with the schedule and all critical items are recognized.
- Weekly/Monthly progress reports prepared, revised and submitted to the Client and Project management Team
- Coordinate the Contractors Planning and scheduling staff.
Project Management, Budget, Management, Primavera, UP
2011 - 2011
job
Lead Planning Engineer
Aker Solutions.
Project name SKULD Project
Client name
Statoil
Work location Oslo, Norway
Tasks
- Prepared the P6 schedule up to level 5 for Tie-Ins and Structures
- Prepared the SAP-PS schedule for levels 6 & 7
- Manpower histograms, s-curves and reports preparation for TAR-2012.
• Integrated the
- Contractors schedules, resource loaded and follow-up their weekly updates.
- CPM analysis and peer review with the construction team in order to ensure the achievement of the SOW in time and within budget
- Weekly/Monthly updates of Primavera/SAP-PS schedules.
- Critical Paths analysis, peer review and recommendations.
- Weekly meetings chaired with Procurement and Engineering Teams to ensure the status is in line with the schedule and all critical items are observed.
- Monthly updated schedule and Critical paths analyzed and issued to the Corporate Team.
- Coordination with the planners for the other Disciplines in order to ensure the activities at the interface are logical linked and proper updated.
- Coordinate the Contractors Planning and scheduling staff.
Client name
Statoil
Work location Oslo, Norway
Tasks
- Prepared the P6 schedule up to level 5 for Tie-Ins and Structures
- Prepared the SAP-PS schedule for levels 6 & 7
- Manpower histograms, s-curves and reports preparation for TAR-2012.
• Integrated the
- Contractors schedules, resource loaded and follow-up their weekly updates.
- CPM analysis and peer review with the construction team in order to ensure the achievement of the SOW in time and within budget
- Weekly/Monthly updates of Primavera/SAP-PS schedules.
- Critical Paths analysis, peer review and recommendations.
- Weekly meetings chaired with Procurement and Engineering Teams to ensure the status is in line with the schedule and all critical items are observed.
- Monthly updated schedule and Critical paths analyzed and issued to the Corporate Team.
- Coordination with the planners for the other Disciplines in order to ensure the activities at the interface are logical linked and proper updated.
- Coordinate the Contractors Planning and scheduling staff.
Budget, SAP, Procurement, Engineering, Primavera, Norway, UP
2010 - 2011
job
Senior Planning Engineer
Technicas Reunidas.
Project name Alliance Refinery Revamping Program
Client name
Alliance Oil Company Ltd
Work location Khabarovsk, Russia
Tasks
- Prepared the schedule for Offsite, Utilities and Interconnections area for the revamping of Khabarovsk Alliance Refinery.
- Prepared the construction schedule for the Tanks Area, Interconnecting Pipe racks and cable racks, U/G piping, new flare, new nitrogen plant and the connection to the new High Voltage City Station.
- CPM analysis and logic review to meet the plan requirements established during the weekly constructability review meetings (accordingly with the availability of construction areas and underground soil contamination and obstacles clearance).
- Prepared look ahead schedules (various time horizons) and issued to the Client to ensure their Operations Department will clear the areas and ensure the safely operation and construction methods are used during the simultaneous works.
• Assist
- Maintenance of the project overall planning requirements.
- Maintenance of overall project schedules for progress and man-hour expenditure.
- Prepared, weekly updates and review of Engineering Documents Register and Procurement Database (scheduled dates) as per construction schedule requirements.
- Responsible for maintaining the Change Control Register and their incorporation into the overall schedule.
Fluor
Position
Client name
Alliance Oil Company Ltd
Work location Khabarovsk, Russia
Tasks
- Prepared the schedule for Offsite, Utilities and Interconnections area for the revamping of Khabarovsk Alliance Refinery.
- Prepared the construction schedule for the Tanks Area, Interconnecting Pipe racks and cable racks, U/G piping, new flare, new nitrogen plant and the connection to the new High Voltage City Station.
- CPM analysis and logic review to meet the plan requirements established during the weekly constructability review meetings (accordingly with the availability of construction areas and underground soil contamination and obstacles clearance).
- Prepared look ahead schedules (various time horizons) and issued to the Client to ensure their Operations Department will clear the areas and ensure the safely operation and construction methods are used during the simultaneous works.
• Assist
- Maintenance of the project overall planning requirements.
- Maintenance of overall project schedules for progress and man-hour expenditure.
- Prepared, weekly updates and review of Engineering Documents Register and Procurement Database (scheduled dates) as per construction schedule requirements.
- Responsible for maintaining the Change Control Register and their incorporation into the overall schedule.
Fluor
Position
Operations, Procurement, Database, Engineering, Logic, Utilities
2008 - 2010
job
Project Controls Scheduler
Taneco.
Work location Nizhnekamsk, Russia
Tasks
- Developed the Construction Schedule for OUIS Area (Offsite, Utilities, Infrastructure and Sulfur Block)
- Prepared and maintained the EPC schedules for Tanks, Interconnecting Pipe rack, U/G Piping, Buildings, HV Cables and Substations, Sulfur Granulation, Storage and Loading, Control Rooms.
- Prepared equipment and bulks RAS (required at site) dates, drawing issue dates, and contract award dates to support the area construction schedule.
- Prepared and/or reviewed all schedules published for the assigned areas. This includes any milestone schedules prepared for inclusion within a contract package, and any ad-hoc
- schedules requested by the Planning Manager.
- Chaired schedule review meeting with Russian Main Contractor and with the Client.
- Updated the new forecasted installation quantities and s-curves accordingly with the detailed design drawings released by the Russian Design Institutes.
- Maintained the Risks Mitigation Register for the designated areas.
- Evaluation and integration of interface milestones within the area schedule.
- Review all schedule submissions prepared by or for contractors.
- Attend any meetings where schedule and progress topics are to be discussed.
- Drawings issuance monitoring and evaluation
- Participate to P & ID review meeting
Fluor
Position
Tasks
- Developed the Construction Schedule for OUIS Area (Offsite, Utilities, Infrastructure and Sulfur Block)
- Prepared and maintained the EPC schedules for Tanks, Interconnecting Pipe rack, U/G Piping, Buildings, HV Cables and Substations, Sulfur Granulation, Storage and Loading, Control Rooms.
- Prepared equipment and bulks RAS (required at site) dates, drawing issue dates, and contract award dates to support the area construction schedule.
- Prepared and/or reviewed all schedules published for the assigned areas. This includes any milestone schedules prepared for inclusion within a contract package, and any ad-hoc
- schedules requested by the Planning Manager.
- Chaired schedule review meeting with Russian Main Contractor and with the Client.
- Updated the new forecasted installation quantities and s-curves accordingly with the detailed design drawings released by the Russian Design Institutes.
- Maintained the Risks Mitigation Register for the designated areas.
- Evaluation and integration of interface milestones within the area schedule.
- Review all schedule submissions prepared by or for contractors.
- Attend any meetings where schedule and progress topics are to be discussed.
- Drawings issuance monitoring and evaluation
- Participate to P & ID review meeting
Fluor
Position
Design, Integration, Support, Infrastructure, Russian, Monitoring, Storage, Utilities, Manager
2003 - 2007
job
Project Controls Scheduler
Tenghiz Chevron Oil.
Project name Second Generation Plant
Client name
Tenghiz Chevron Oil
Work location Tengiz, Kazakhstan
Tasks
- Planning and scheduling activities for TCO Second Generation Project / Sour Gas Injection in Tengiz Oilfield, Kazakhstan.
- Prepared and maintained the EPC schedules for LPG Storage and Loading, Sulfur Granulation, Storage and Loading, New Changing Room, Fire Station, Crude Tanks, Interconnecting Pipe rack.
- Maintained and updated the area level III construction schedule in accordance with defined cut-off dates.
- Prepared equipment and bulks RAS (required at site) dates, drawing issue dates, and contract award dates to support the area construction schedule.
- Prepared and/or reviewed all schedules published for the assigned areas. This includes any milestone schedules prepared for inclusion within a contract package, and any ad-hoc schedules requested by the Planning Manager.
- Evaluation and integration of interface milestones within the area schedule.
- Review and approve all schedule submissions prepared by or for contractors.
- Maintenance of the Mile Marker progress system.
- Reporting of weekly physical progress (versus plan) and production of the weekly area construction report.
- Review of CWP status and forecasting of work-front availability.
- Monthly report input - reporting of monthly accomplishments plans for next period, areas of concern and mitigation's.
- On-the-job training for local planning technicians.
- Attend any meetings where schedule and progress topics are to be discussed.
- Steelwork and spools fabrication tracking
- Manpower reports and forecasts
Saipem SA
Position
Client name
Tenghiz Chevron Oil
Work location Tengiz, Kazakhstan
Tasks
- Planning and scheduling activities for TCO Second Generation Project / Sour Gas Injection in Tengiz Oilfield, Kazakhstan.
- Prepared and maintained the EPC schedules for LPG Storage and Loading, Sulfur Granulation, Storage and Loading, New Changing Room, Fire Station, Crude Tanks, Interconnecting Pipe rack.
- Maintained and updated the area level III construction schedule in accordance with defined cut-off dates.
- Prepared equipment and bulks RAS (required at site) dates, drawing issue dates, and contract award dates to support the area construction schedule.
- Prepared and/or reviewed all schedules published for the assigned areas. This includes any milestone schedules prepared for inclusion within a contract package, and any ad-hoc schedules requested by the Planning Manager.
- Evaluation and integration of interface milestones within the area schedule.
- Review and approve all schedule submissions prepared by or for contractors.
- Maintenance of the Mile Marker progress system.
- Reporting of weekly physical progress (versus plan) and production of the weekly area construction report.
- Review of CWP status and forecasting of work-front availability.
- Monthly report input - reporting of monthly accomplishments plans for next period, areas of concern and mitigation's.
- On-the-job training for local planning technicians.
- Attend any meetings where schedule and progress topics are to be discussed.
- Steelwork and spools fabrication tracking
- Manpower reports and forecasts
Saipem SA
Position
Forecasting, Training, Integration, Support, Storage, Production, Manager
2006 - 2006
job
Fabrication Yard Planning Engineer
Exxon Mobil.
Project name Dalia, Marimba, Kizomba,E.A.
Client name
Total, Exxon Mobil
Work location Soyo, Angola
Tasks
- Planning and scheduling activities for Company projects in Soyo Fabrication Yard, Angola. The mission of the yard covers the fabrication of components for Offshore - Deep Water Projects in Angola.
- Prepared and maintained the fabrication, testing and load out schedules for subsea spools, risers, anchoring piles, topside structures, manifolds, umbilical accordingly with their delivery to offshore plan requirements.
- Attend the internal progress meetings as well as with the customers (Total, ExxonMobil, BP, Saibos, FMC)
- Prepared and maintained the histograms and s-curves for these schedules
- Weekly and monthly reports including CPM analysis, procurement risks and engineering impacts.
Sicim SpA
Position
Client name
Total, Exxon Mobil
Work location Soyo, Angola
Tasks
- Planning and scheduling activities for Company projects in Soyo Fabrication Yard, Angola. The mission of the yard covers the fabrication of components for Offshore - Deep Water Projects in Angola.
- Prepared and maintained the fabrication, testing and load out schedules for subsea spools, risers, anchoring piles, topside structures, manifolds, umbilical accordingly with their delivery to offshore plan requirements.
- Attend the internal progress meetings as well as with the customers (Total, ExxonMobil, BP, Saibos, FMC)
- Prepared and maintained the histograms and s-curves for these schedules
- Weekly and monthly reports including CPM analysis, procurement risks and engineering impacts.
Sicim SpA
Position
Procurement, Engineering, Offshore, Testing, Spa
2004 - 2006
job
Planning Engineer
AGIP.
Project name Eskine West Onshore Processing Plant
Client name
AGIP
Work location Atyrau, Kazakhstan
Tasks
- Prepared construction schedules from Site Preparation and Piles Installation through equipment erection- AGIP KCO Eskine West Project.
- Prepared construction schedules for Initial Civil Works: pipe rack foundations, internal main roads and protection fence.
- Prepared construction schedules for Plant Utility: Pump house, compressors, water treatment buildings, auxiliary pipe rack and equipment foundations,
- Prepared construction schedules for Metito Equipment and Boilers installation, Pipe racks, piping and supports fabrication and installation - Bateman / AGIP KCO
- Prepared construction schedules for Main Works - Piling and foundations for pipe racks and industrial buildings in oil, gas and Sulphur treatment areas North Caspian Constructors / AGIP KCO
- Weekly updates based on contractors schedules and construction status
- Manpower histograms and s-curves
- Daily/Weekly/Monthly reports for three different contracts (AGIP-KCO, Bateman and Gate)
- Weekly progress meetings and schedules review with customers
- Daily progress meetings with sub-contractors
- Tender schedules prepared for new contracts
- Budget plans prepared for one year look ahead schedules.
- Coordinate the internal planning, document control and procurement staff
- Liaise with the customers departments in order to ensure schedules compatibility with their requirements
Astaldi
Position
Client name
AGIP
Work location Atyrau, Kazakhstan
Tasks
- Prepared construction schedules from Site Preparation and Piles Installation through equipment erection- AGIP KCO Eskine West Project.
- Prepared construction schedules for Initial Civil Works: pipe rack foundations, internal main roads and protection fence.
- Prepared construction schedules for Plant Utility: Pump house, compressors, water treatment buildings, auxiliary pipe rack and equipment foundations,
- Prepared construction schedules for Metito Equipment and Boilers installation, Pipe racks, piping and supports fabrication and installation - Bateman / AGIP KCO
- Prepared construction schedules for Main Works - Piling and foundations for pipe racks and industrial buildings in oil, gas and Sulphur treatment areas North Caspian Constructors / AGIP KCO
- Weekly updates based on contractors schedules and construction status
- Manpower histograms and s-curves
- Daily/Weekly/Monthly reports for three different contracts (AGIP-KCO, Bateman and Gate)
- Weekly progress meetings and schedules review with customers
- Daily progress meetings with sub-contractors
- Tender schedules prepared for new contracts
- Budget plans prepared for one year look ahead schedules.
- Coordinate the internal planning, document control and procurement staff
- Liaise with the customers departments in order to ensure schedules compatibility with their requirements
Astaldi
Position
Budget, Contracts, Procurement, Processing, Contracts
2003 - 2003
job
Planning Manager
Romanian National Company of roads administration.
to Constanta
Client name
Romanian National Company of roads administration
Work location Bucharest, RO
Tasks
- Schedule prepared, updated and reporting for the Construction of Bucharest-Constanta Highway
- Integrate the contractors schedules into the master plan
- Weekly updates and reporting to the client and to the project consultant teams
- Internal schedule weekly review meetings chaired with the Construction, Procurement, Engineering, QC and HSE staff
Client name
Romanian National Company of roads administration
Work location Bucharest, RO
Tasks
- Schedule prepared, updated and reporting for the Construction of Bucharest-Constanta Highway
- Integrate the contractors schedules into the master plan
- Weekly updates and reporting to the client and to the project consultant teams
- Internal schedule weekly review meetings chaired with the Construction, Procurement, Engineering, QC and HSE staff
Administration, Procurement, Engineering, QC, Manager
2002 - 2003
job
Project Controller
Gitto Costruzione.
Project name Construction of Highway from Bodo To Bonny
Client name
Nigarian National Company for roads administration
Work location Port Hartcourt, Nigeria
Tasks
- Schedule prepared, updated and reporting for Construction of Bodo-Bonny Highway.
- Engineering and Procurement schedules prepared to meet the constructions schedule requirements
- Prepared the Project staffing plan and budget allocation.
- Coordinate with other projects schedules in order to ensure sufficient resources are allocated.
- Managed the Technical Office, Finance and HR departments as additional job duties
Client name
Nigarian National Company for roads administration
Work location Port Hartcourt, Nigeria
Tasks
- Schedule prepared, updated and reporting for Construction of Bodo-Bonny Highway.
- Engineering and Procurement schedules prepared to meet the constructions schedule requirements
- Prepared the Project staffing plan and budget allocation.
- Coordinate with other projects schedules in order to ensure sufficient resources are allocated.
- Managed the Technical Office, Finance and HR departments as additional job duties
Administration, Budget, Procurement, Finance, Engineering, Office
2001 - 2002
job
Planner
Techint.
Project name Construction OF LNG Train #3
Client name
Shell
Work location Bonny Island, Nigeria
Tasks
- O&G Construction works in Bonny Island for NLNG (A Shell subsidiary company)
- Mechanical, E&I schedules prepared and issued to the client
- Liaise with TSKJ Consortium staff for schedule review and acceptance
- Integrated the sub-contractors schedules
- Mentoring the local staff
Client name
Shell
Work location Bonny Island, Nigeria
Tasks
- O&G Construction works in Bonny Island for NLNG (A Shell subsidiary company)
- Mechanical, E&I schedules prepared and issued to the client
- Liaise with TSKJ Consortium staff for schedule review and acceptance
- Integrated the sub-contractors schedules
- Mentoring the local staff
Mentoring
1996 - 2001
job
IT Systems Specialist
S.N. Nuclearelectrica S.A.
Project name Nuclear Full Scope Training Facility
Client name
S.N. Nuclearelectrica S.A.
Work location Cernavoda, RO
Tasks
- Supervised the Hardware and Software Maintenance of Nuclear Full-Scope Training Simulator
- Lead the Process Modeling Group in order to ensure the full compliance of the Simulator with the Main Control Room
- Liaise with Romanian Nuclear Authority and CAE (simulator manufacturer) for integration, tests, commissioning and acceptance of the NFT Simulator
- Integrated the Nuclear Training Centre Computer LAN into the NPP LAN and databases connections
- Developed a Nuclear Training System Database to support the Systematic Approach Training for Nuclear Operator Licensing Process
- Mentoring the junior staff
IFT - Iasi
Position
Client name
S.N. Nuclearelectrica S.A.
Work location Cernavoda, RO
Tasks
- Supervised the Hardware and Software Maintenance of Nuclear Full-Scope Training Simulator
- Lead the Process Modeling Group in order to ensure the full compliance of the Simulator with the Main Control Room
- Liaise with Romanian Nuclear Authority and CAE (simulator manufacturer) for integration, tests, commissioning and acceptance of the NFT Simulator
- Integrated the Nuclear Training Centre Computer LAN into the NPP LAN and databases connections
- Developed a Nuclear Training System Database to support the Systematic Approach Training for Nuclear Operator Licensing Process
- Mentoring the junior staff
IFT - Iasi
Position
Training, Mentoring, Database, Integration, Compliance, It, Support, Hardware, Software
1990 - 1996
job
IT Specialist
IFA.
May 1990 - June 1996
Project name Development of various Computer Assisted Equipment for Nondestructive Testing in Nuclear Industry
Client name
IFA - Bucharest
Work location Iasi, RO
Project name Development of various Computer Assisted Equipment for Nondestructive Testing in Nuclear Industry
Client name
IFA - Bucharest
Work location Iasi, RO
It, Testing, Development
1988 - 1990
job
IT Systems Engineer
Comtom S.A.
Project name Data Processing Center - (HW & SW)
Client name
COMTOM S.A.
Work location Iasi, RO
Client name
COMTOM S.A.
Work location Iasi, RO
It, Processing
My education
Technical University Iasi Romania
Bachelors, Education
Bachelors, Education
Viorel's reviews
Viorel has not received any reviews on Worksome.
Contact Viorel Iftimi
Worksome removes the expensive intermediaries and gives you direct contact with relevant talent.
Create a login and get the opportunity to write to Viorel directly in Worksome.
are ready to help you
and get specific bids from skilled talent in Denmark